Culvert Lining | Newburn, England, UK

200m² of CC8® Installed for Scour Protection of an Old Brick-Built Culvert

200
of CC8® installed within the culvert
5 days
to complete installation in confined conditions
4-person
crew delivered works without specialist plant

Design & Installation

  • CC8® Batched Rolls used

  • Water diverted through a 600mm pipe

  • Debris cleared and voids grouted to fill scour holes

  • Secured at perimeter egdes using anchors and sealed with grout
  • Anchors used to join layers

  • Hydrated using diverted culvert water

Securing leading edge of CC to culvert wall

Summary

A 4-person crew completed 200m² of CC8® installation in just 5 days, despite restricted space and limited light. The culvert lining now provides durable scour and erosion protection, safeguarding the structure against future flood events and debris impact. CC8® offered a cost-effective, low-maintenance alternative to traditional methods, proving ideal for complex culvert remediation.

Completed section of CC installation within the culvert below Spencer Court