Skip to content

Search Concrete Canvas

Channel Lining | Batangas, Philippines

324m² of CC8® Installed for Roadside Drainage

324
of CC8® used to provide channel lining solution
6 Person
crew carried out the installation
3 Weeks
for installation to be completed

Design & Installation

Prior to the installation, the slope was graded and compacted to ensure a smooth surface on which to install the CC. Anchor trenches were then prepared at the crest and toe of the slopes, with the contractor taking care to ensure the excavation of the anchor trenches did not disturb or damage the lining below the top soil.

Bulk rolls of the specified CC5® were mounted on a spreader beam and suspended from a boom truck at the crest of the slopes for easy deployment. The material was unrolled down the slope, laid vertically with subsequent layers overlapping the last by 100mm. The leading and trailing edges of each length of CC material were captured within the anchor trenches and secured to the substrate using ground pegs at 0.5m intervals. The material below each overlap was hydrated and the upper layer replaced prior to jointing of the overlaps using stainless steel screws applied in a zig zag pattern at 50mm centres. Once each section was completed, the material was hydrated using a water tank and hose with sprinkler head attachment and the anchor trenches backfilled using marl. Where CC terminated against concrete sleepers, stainless steel strips and bolts were used to prevent ingress below the material and ensure a neat termination detail.

CC was easily installed around existing infrastructure
Completed section of roadside channel

Summary

A total of 23,700m² of CC5® material were installed by a local contractor. A team of ten carried out the works over 24 days, with around ten hours worked per day in hot, dry conditions.

This rate of installation would not in any way be possible using conventional concrete and was not technically viable with the alternative solutions considered for the project. The client had provided a very tight deadline for this project, as they had to make part of the pond operational. The use of CC on this project meant the installation was completed well before the deadline. The project was highly successful, particularly in terms of time savings and ease of installation for the contractor.

CC easily accommodates existing infrastructure

Choose CC For Your Channel Lining Solution