Skip to content

Search Concrete Canvas

Channel Lining | Coalcleugh, Hexham, Northumberland, UK

700m² of CC8® installed as erosion control to a newly formalised channel

700
of CC8® used to line the drainage channel
7 weeks
to complete during extreme weather conditions
100mm
overlaps secured with screws for durability

Solution

A lining solution was required for the formalised channel to provide erosion control in order to ensure the channel is able to accommodate high water levels and rapid flow rates. Having previous experience of Concrete Canvas® the client – the Coal Authority – included CC in the project designs from the offset with no alternatives considered.

This was due to the rapid installation rates of the material and the ease of install in such a remote location. The works were carried out by a contractor who was also familiar with CC having installed the material on numerous Coal Authority projects.

Rock Rolls used to backfill anchor trenches in difficult to access locations
Anchor trenches used to capture CC edges where possible

Design & Installation

  • Small excavator used to cut new channel
  • Batched and Bulk Rolls of CC8® were specified
  • Transverse layup
  • Screwed overlap joint
  • Downstream, the material was terminated into a drystone wall
  • Upstream, the material was terminated into a sandbag headwall
  • Edges of CC8® were secured within anchor trenches using ground pegs, backfilled with soil where possible, or rock rolls, or larger stones.
  • Hydrated using diverted stream
Where anchor trenches were not possible, rock rolls and stones were used

Summary

The installation was carried out by a team of four over several weeks. One of the advantages of using CC in a transverse layup is that the installation can be halted quickly if needed, which was necessary on this scheme as several extreme weather events and floods required the channel to be quickly reopened. A total of 700m² of CC8® was successfully installed in difficult weather conditions

Upstream headwall

The use of Concrete Canvas on the scheme at Coalcleugh was certainly the right material for the job in what was a remote site with difficult topography under some extremely challenging weather conditions. Where ground conditions varied and required quick modifications to the design, the team at Concrete Canvas supported and provided advice for solutions very quickly so as to mitigate any potential delays to the project.

Rob Culledge Contracts Manager, JN Bentley

Reinforce Your Channel for Long-Term Erosion Protection