Channel Lining | Recife, Pernambuco, Brazil

Environmentally Sensitive Channel Lining with CC8

1125ft²
of CC8 used to line the channel
10 Days
to install with a team of six
9 Rolls
bulk rolls used for channel and slope

Solution

Evelliquas dolorundi sanditios am, conserumet rem quatus erchilis modicimus, suntibusae doluptas mosam, eiur sin cum faccaepratia vellace ribuscia non nosantum lab ipis comni imendunt velende liquatur, siminum nusant vendae vel ex et quis sandenducid quibearis explia sum quis dolores ciumet elis et et unt la quatus rehenda erchicat laborisqui tenderrum enihilibus.

Design & Installation

Prior to installation, all existing vegetation from the site was removed as far as the tree line, which, due to environmental restrictions, could not be touched by the team. The drainage of the site was then considered before the CC was laid transversely across the channel, allowing for variations in profile length, with layers overlapping by 100mm in the direction of water flow. The CC was then fixed to the substrate and layers secured at the overlaps. Following installation, a coconut fibre was installed along the slopes surrounding the channel to promote vegetation growth.

Coconut fibre was fixed to slopes around the channels after installation
The completed installation revisited

Summary

1,125m² of CC8 was installed over a period of ten days by a team of six people, while the project as a whole took three weeks due to the addition of the coconut fibre. A total of nine bulk rolls were required for the channel lining, and some CC was used for slope protection where required.