Channel Lining | Killaloe, Ireland
47% Carbon Saving for Killaloe Bypass with CCT2™
Background
Channel Preparation: site evaluation, excavation, re-profiling and deployment of CC8™
1500m²
of CC8™ used to line the drainage channel
12 Days
while the team of six also worked on additional projects
100mm
overlaps secured with screws for durability
Solution
Design & Installation
Conclusion
In total, 1,500m2 of CC8™ was installed in 12 days while the team of six also worked on additional projects. The installation was deemed a complete success, the contractors were happy with the solution that CC8™ provided for lining the drainage channel.